June 28, 2024 Update

The Conference Center and Market have advanced past most inwall and above ceiling inspections and have started to enclose all interior walls and ceilings. Tenants will also notice the sheathing advancing on the exterior of the Conference Center and framing moving forward on the Center Amenity. As work
advances inside Towers 4 and 5 (2555 and 2575), Tenants will once again have access to the South Entry of Tower 5 where the new pavers have been installed. Relocating our fitness center up to the new second floor of the Center Amenity meant creating a new floor assembly to isolate that gym/studio
activity from the Amenity spaces below. The GC is near completion on a floor assembly on the second floor that will isolate that activity from the Café, Private Dining and Parlor spaces below...and don’t forget to download the app to book our spaces!

​

Upcoming

As we work to complete the shade structure and gateway framing – the roof patch-back for those
structural supports is underway. On the underside at that same area - the GC is close to closing in
those retail colonnade ceilings and sheathing the exterior bulkhead and fascia. Work is also advancing
that may not be as visible to the Tenants but is critical to the success of the project; the plumbing and
infrastructure for the Center Amenity kitchen and bar has been installed an inspected and we’ll be
installing a new Grease Interceptor on the B1 level of the parking structure below...along with the steel
needed to support that on the B2 Level. Please be mindful as you navigate those areas of the garage in
the upcoming weeks.

​

June 17, 2024 Update

The foundation of the shade structure between the new Conference Center and the Center Amenity
Building has been installed. The center plaza shade structure is advancing with connections to the 1-
story retail buildings already moving forward. The metal deck is in place on the Center Amenity roof
and the 2nd floor. Layton has advanced and the concrete slab is now in place on the new second floor opening the way to new MEP overhead work. Additionally, the first pavers have been implemented
behind Tower V’s south entrance. We are excited to announce that Tower V’s south entrance is opening
today, June 17. Thank you again for your continued patience while we work through the
improvements. ...and don’t forget to download the app to book!

​

Upcoming

Construction progress continues as the drywall has been hung in the conference center. Masonry work has also begun for the wall behind the amenity building. Additionally, drywall installation and finishings on the Tower I & II exterior soffits on the north side of the building will commence in the coming weeks.
The last steel for the center canopy, including the Gateway featuring the Esplanade name, and the South canopy columns to start next week on the south side; all canopy steel to be stood by Monday 6/24.

​

May 28, 2024 Update

While the Lobbies have delivered in Towers 1 and 2, improvements in Towers 4 and 5 are now underway. The framing is advancing quickly in Tower 5 lobby and select upper floor improvements have continued to advance. Expect to see flooring changes taking place in the Lobby of Tower 4 over the weekend of the 31st.

 

Thank you again for your continued patience while we work through the improvements. ...and don’t forget to download the app to book!

​

Upcoming

As noted in our last update, the shade structure between the new Conference Center and the Center Amenity Building has been installed. In addition – you should see the center plaza shade structure advancing over the next two weeks with connections to the 1-story retail buildings already moving forward. We noted previously that the metal deck was in place on the Center Amenity roof and the 2nd floor. Layton has advanced and the concrete slab is now in place on the new second floor opening the way to new MEP overhead work. Exciting to see the new elevator framing in place

 

May 10, 2024 Update

The Lobby construction has been completed. Look out for the new phone rooms, huddle rooms, and wellness rooms, all of which are ready to be utilized! We encourage you to explore and take advantage of these new spaces.


Additionally, room booking is available and turned on. Download the app to book!
Central Amenity Building is topped out, the steel erection is now complete.

​

Upcoming

​

Common area improvements in Towers IV and V are well underway and the ground-plane enhancements between Towers IV and V have commenced. The center plaza and the east and west wings are taking shape with the first area of new waterproofing, topping slab and concrete banding in place on the west
side and new planters already formed on the east side of the Plaza.Metal decking on the roof and second floor is complete and both new stairs have been installed at
Center Amenity and Layton has started the process of installing the new elevator.

 

While the new exterior envelopes start to take shape on both the Conference Building and the new Center Amenity, framing for the new shade structure will begin to be installed this coming week. Lastly, look for a new shade structure to connect the Conference Building to the Center Amenity to be installed this weekend!

 

April 5, 2024 Update

Towers I and II are expected to reach completion this coming week, on April 8, with the delivery of furniture.


Look out for upcoming events and communications regarding the opening of huddle rooms, conference rooms, and wellness rooms as they are ready for use.

​

Upcoming

As we wrap up finishing touches in Tower I and Tower II and complete the furniture installation in those spaces – our focus has shifted to our next objectives. Tower IV and V improvements have recently commenced with demolition and make-safe work.


The ground-plane improvements are taking shape with the first area of new waterproofing in place and the first of the new planters being formed on the West side of the Plaza.
The second story of steel on the central amenity building continues to rise and take shape. The steel for the new shade structure is scheduled to start rising by the end of the 2nd week in April. We are looking forward to expanding that scope closer to the center plaza and appreciate everyone’s patience as we work through these new layers.

 

March 22, 2024 Update

This week you will see the steel rising to the 2nd level of the Center Amenity Building, with a goal to complete majority of that phase of steel by the end of this month. 

​

Looking ahead, the steel for the new shade structure is scheduled to start rising by the end of the 2nd week in April. The first portion of waterproofing and topping slab has been completed on the western plaza in advance of new pavers.  We are looking forward to expanding that scope closer to the center plaza and appreciate everyone’s patience as we work through these new layers. 

​

Upcoming

As we wrap up finishing touches in Tower I and Tower II and complete the furniture installation in those spaces – our focus will shift to our next objectives. Tower V improvements started this past week, and Tower IV improvements will begin this coming week. The Conference Center interiors are beginning to take shape with much of the plumbing and electrical rough-in completed within the new framing.  Our AV/IT teams will mesh-in this coming week to install the backbone infrastructure for our more expansive Conferencing and Meeting program. 

 

March 8, 2024 Update

The Lobbies in Towers I (2425) and II (2525) will begin to be operational this month, as we aim to finish the full scope of the lobby work in the next few weeks. The first-floor restrooms, Mother’s Room, and wellness rooms will be ready for use in the coming weeks. In addition, you will begin to hear the new sound system that has been integrated into the Lobbies come online.


As our new huddle rooms, health and wellness suites, as well as our Team Building suite near completion, you will be able to book those spaces via the Esplanade App. For now, as they open in the coming weeks, they will be available on first come first serve basis.
 

February 23, 2024 Update

The Lobbies in Towers 1 (2425) and II (2525) will begin to be operational in the coming weeks, as we aim to finish the full scope of the lobby work in the early weeks of March. Furniture and accessories for both towers will be arriving starting March 1. The restrooms will also be fully operational. As our new huddle rooms, health and wellness suites, as well as our Team Building Suite near completion, you will be able to book those spaces via the Esplanade App. For now, as they open in the coming weeks, they will be available on a first come first serve basis. 

 

February 9, 2024 Update

​

The latest update on the delivery of a crane that will be erecting the steel for the new Central Amenity
Building: Weather has delayed some of the preparation for the new steel and this equipment will now be delivered on February 9th (weather permitting). With that
pending, we will continue to have flaggers direct traffic through the fenced area of the central plaza. The morning work of paver and concrete removal at the plaza level between Towers I and II will continue from 7AM – 8:30AM daily for the next 4 weeks. Additionally, we have added Saturdays to our schedule for this work, which will take place from 7AM – 3PM for the next four weeks.

​

Home-stretch work continues in Towers I (2425) and II (2525) with Layton and our Integration partners
advancing the Lobby and Common Area improvements. These improvements include lighting, AV and IT scope which are being integrated into these new spaces while the GC advances final millwork and finish details. Exterior work on these two towers is also taking form with exterior framing of the higher ceilings and fascia that will frame the views thru that improved colonnade. Finally, Layton has
advanced with framing and started rough-in of the new program spaces in our Conference Center and
grab and go market.

 

January 26, 2024 Update

​

The first phase of the project that will be delivered are the Lobbies in Towers I(2425) and II(2525). Slated for completion the second week of February the new lobbies will include new wellness rooms, huddle rooms, and an innovative team building suite.

 

The team building suite will be a bookable space with a sports simulator and conferencing capabilities.
More information on availabil
ity and how to book this space will be coming out soon, and will be available via the Esplanade app.

​

Upcoming Construction

​

Upcoming construction in the next two weeks will include the delivery of a crane that will be erecting the steel for the new Central Amenity Building. This equipment will be delivered on February 5th, and as such we will continue to have flaggers direct traffic through the fenced area of the central plaza. The morning work of paver and concrete removal at the plaza level between Towers I and II will continue from 7AM – 8:30AM daily for the next 4-6 weeks. Additionally, we have added Saturdays to our schedule for this work, which will take place from 7AM – 3PM for the next four weeks.

​

​

​

​

​